Construction Update 09-06-2020
Basement 1 & 2, Ground Floor (Retail), Level 1 Apartments & Level 2 Apartments are now all Structurally Complete!
Level 3’s Concrete Floor Pour has been completed and the structural walls between Apartment Levels 3 and 4 are being installed over the next week to two weeks.
Prefabricated concrete components are continuously being delivered to site, the next big construction milestone is pouring the concrete floor for Apartment Level 4, commencing in 28 days.
2 more floor pours and 1 roof required to structurally complete our building!